Vermilion 342
After the original discovery well was drilled, Arena acquired a 50% interest in the project and was named operator of the development. Arena installed the production platform and pipeline and drilled and completed the existing wells. Production from the platform is processed at Arena’s nearby EC 328B facility. Based on encouraging initial performance, additional development activity is planned for this field.
Production Start
April 2013
Gross Production - Current
3,000 BOEPD
Wells Drilled By Arena To Date
5 Wells
Water Depth
223'
Platforms
1 6-Slot, 3-Pile Platform
Processing Capacity
5,500 BOPD
10 MMCFGPD
7,500 BWPD